Shanghai BASF coating project environmental impact assessment publicity
issued by: Shanghai Research Institute of chemical industry
release date: March 1, 2010
1. Description
Shanghai Research Institute of chemical industry is entrusted by Shanghai BASF chemical coating Co., Ltd. to carry out the environmental impact assessment of the new coating production plant construction project of Shanghai BASF chemical coating Co., Ltd. The first information release is now made to the public in accordance with national and municipal laws and regulations
Shanghai basif chemical coating Co., Ltd. and Shanghai Research Institute of chemical industry are responsible for the authenticity of the information released at this stage. With the implementation process of the project and the implementation of environmental impact assessment, relevant information will be improved or adjusted
2. Outline of the construction project
(1) project name: construction project of new paint production plant of Shanghai bashifu chemical coating Co., Ltd.
(2) project location: Fengxian District, Shanghai Chemical Industry Zone
(3) industry of the project: chemical raw materials and chemical products manufacturing industry
(4) project content: annual output of 17000 tons of various paints, Among them, PU polyurethane paint (2500 tons of varnish and 1500 tons of paint), nitro paint (500 tons of varnish and 400 tons of paint), water-based wood paint (50 tons of varnish and 50 tons of paint), 100 tons of fire-retardant paint, 600 tons of mixed paint, 100 tons of chlorinated rubber alkyd hull paint, 100 tons of car cover varnish, 100 tons of fluorocarbon paint, 1000 tons of epoxy floor paint, 5000 tons of water-based interior and exterior wall emulsion paint, 1500 tons of TDI adduct, 500 tons of TDI Trimer 500 tons of low molecular polyamide curing agent, 300 tons of PU polyurethane paint thinner, 800 tons of NC thinner, 200 tons of 4# lacquer pine perfume, and 1200 tons of PU polyester paint general thinner
3. Overview of the construction unit
(1) name of the construction unit: Shanghai bashifu chemical coating Co., Ltd.
(2) address of the construction unit: No. 555, Chugong Road, chemical industry zone, Shanghai
(3) contact person of the construction unit: Mr. Yu
(4) contact method of the construction unit:
4 Summary of the evaluation organization
(1) name of the evaluation organization: Shanghai Research Institute of chemical industry
(2) certificate number of the evaluation organization: EIA Zheng Jia Zi No. 1806
(3) address of the evaluation organization: Building 8, 345 Yunling East Road, Putuo District, Shanghai
(4) contact person of the evaluation organization: Guo Gong, Xiao Chen
(5) contact information of the evaluation organization
: × 1634, 1685
Fax:
e_ Mail:kydeia2008@
5. Working procedures and main work contents of environmental impact assessment main procedures of environmental impact assessment: on the basis of verifying the engineering data and determining that the source base of the project can produce a new mechanical ductile polymer that can solve the existing problems, combined with the environmental status quo and environmental protection objectives of the construction area, analyze the degree and scope of environmental impact of the project and evaluate the feasibility of the project construction; Put forward requirements and suggestions for environmental protection measures in combination with national environmental protection policies and regulations, public opinions and environmental impact analysis results
the main work contents of environmental impact assessment include: being able to detect the current environmental quality investigation, pollution source investigation, engineering analysis, cleaner production analysis, environmental impact prediction and assessment, environmental risk assessment, pollution prevention and control countermeasure analysis, public participation, environmental management and monitoring plan, and The purpose of environmental impact economic profit and loss analysis, planning compatibility analysis, total amount control and other contents is to predict the impact of the project on the surrounding environment after the completion of the project, and put forward corresponding environmental protection measures by understanding the current situation of project sewage discharge and environment
note: the reprinted content is indicated with the source. The reprint is for the purpose of transmitting more information, and does not mean to agree with its views or confirm the authenticity of its content
LINK